WP01- RF (AdE)

CFT ok. 15th septembermeeting to evaluate offers

All components list is ok and data has been provided to WP05 feasibility study

Spinner proposed some development for an invacuum S-band RF isolator. We will likely opt for an SF6 solution. 

 

WP02- Diag (FE)

Laser: itterbium telluride crystal laser from Ligth-conversion (lithuania) is compact (80x60x30 cm) sturdy, reliable (no realignment). The laser cooling system can be placed up to 50m far from the source. This system is also used by other accelerator facility in the world, such as ARES at DESY. FE is in contact with the relevant people.  

 

WP03- Vacuum (HPM)

CDR SwisFEL mentions 16mm diameter chambers. This is feasible also for COLD.

AdE: vacuum valves for C-band waveguides?

HPM: yes from VAT

 

WP04- Mechanical Engeneering (TB)

no changes. meeting with SLAC. missing drawing of parts such as the structures in the quarter modules (and rafts) and the interface components to the external equipment.

Must obtain a drawing of the exiting infrastructure in the linac and slides from last meeting (ACTION). 

PB: this is available. Infrared scan performed for linac refurbishment.

 

WP05-Infrastructure (SL, on behalf of YG)

Docuement feasibility being filled. Reminder to every one to contribute to the document.

 

WP06-Operation (JLR)

Presentation of installation steps including Linac refurbishment and COLD project.

BJ: Section 0 and diag-bump are on a girder already? 

PB/VS:  Section 0 is on a girder

(SL note post meeting: diag and dump need to be designed and are going to be on a dedicated girder as well)

VS: more equipment, cubicles, spares. This will require more space and space is presently FULL. 

VS: in safety autorizations LN2 hazard should be considered for interventions in the tunnel

VS: dust close to the modulators at the linac entrance will be an issue. A second wall or SAS should be installed to isolate from the exterior.

BJ: the RF test cage has to stay in place?

VS: after assembly of the spare thermoionic gun it will not be needed, could be dismantled (and kept somewhere)

SW: the linac section 0, buncher and gun, should exit the tunnel before installation of COLD. This will make space and will probably simplify ASNR approval. also the problem of dust is reduced if the COLD installation is closer to the existing linac.

proposal: On Step3 verify if the linac refurbishment stays in the tunnel. Add a intermediate step with removal of Section0 and spare thermoionic gun.  (ACTION)

GLB: supports the idea of SW and adds that in the place of Section0 an undulator could be placed

GLB: ASNR should be informed if undulators are one of the steps of the installation

GLB: a WP-photons could be added to the project

 

WP07-Control (RB)

no news. if new equipment, contact RB.

Also the rack "U" requirements for installations are moved from Control list to Operation List for WP05-infrastructure feasibility  (ACTION)

WP08-Alignment (no news)

WP09-Safety (P.C.: meeting scheduled with FLUKA expert for ASNR documentation)

WP10-Magnets (GLB)

 

WP-11-Beam Dynamics (SL)

Simulations are more and more similar to the results produced at Frascati.

 

Humar Resources

QQ: work in progress

SW: may be COD positions could be opened? QQ: may be.

 

There are minutes attached to this event. Show them.
    • 11:05 AM 11:10 AM
      general project update 5m

      Change of name (COLD = Cool copper Operation Linac Driver)

      Speaker: Simone Liuzzo (ESRF)
    • 11:15 AM 11:20 AM
      WP status round table 5m

      WP 01 RF
      WP 02 Diagnostics
      WP 03 Vacuum
      WP 04 Mechanical Engineering:
      WP 05 Infrastructure
      WP 06 Operation
      WP 07 Control
      WP 08 Alignment
      WP 09 Safety (P.C.: meeting scheduled with FLUKA expert for ASNR documentation)
      WP 10 Magnets
      WP 11 Beam Dynamics

    • 11:35 AM 11:40 AM
      WP01: RF 5m

      CFT

      Speaker: Alessandro D'Elia (ESRF)
    • 11:45 AM 11:50 AM
      WP02-Diagnostics 5m

      discussion about diagnostic+dump to be used for linac refurbishment and cold project

      beam size
      energy
      emittance
      bunch length
      beam losses
      current
      beam dump

      Speakers: Friederike Ewald (ESRF), Marc Dubrulle, Simone Liuzzo (ESRF)
    • 11:55 AM 12:05 PM
      WP05-infrastructure 10m

      informations needed for feasibility study

      Please fill this document or write to S.Liuzzo:
      https://cloud.esrf.fr/apps/files/files/16443002?dir=/COLD/WP05%20Infrastructure&openfile=true

      Speaker: Yann Gouez (ESRF)
    • 12:10 PM 12:18 PM
      WP06-operation: plan of installation 8m
      Speaker: Jean-Luc Revol (ESRF)
    • 12:20 PM 12:35 PM
      WP11 Beam Dynamics 15m

      COLD project set up multi particle tracking simulations

      Speaker: Simone Liuzzo (ESRF)
    • 12:35 PM 12:45 PM
      Review CDR document 10m

      Conceptual Design Report:
      https://www.overleaf.com/7899755955tmcgtsjgcdkt#10571a

    • 12:45 PM 12:55 PM
      Planning and budget review 10m

      JIRA planning
      https://jira.esrf.fr/secure/PortfolioPlanView.jspa?id=26&sid=26&vid=0#plan/backlog

      Speaker: Simone Liuzzo (ESRF)
    • 12:55 PM 1:05 PM
      Human resources 10m
    • 1:05 PM 1:15 PM
      AOB 10m

      LTSP document:
      https://www.overleaf.com/read/nsvfrbjwfykb#effb67

      List of pending action:
      https://confluence.esrf.fr/display/PROJCOLD/Meeting+notes

      As requested by the SLAC colleagues, An abstract is submitted and accepted for a talk at the LCWS workshop in October, Valencia:
      https://agenda.linearcollider.org/event/10594/abstracts/

    • 1:15 PM 1:25 PM
      update confluence page 10m

      check Pending Actions list from previous meetings

      https://confluence.esrf.fr/display/PROJCOLD/COLD%3A+Cool+copper+Operation+Linac+Demonstrator