Full energy linac - Impact of the building on the infrastructures

→ Europe/Paris
CTRM meeting room

CTRM meeting room

Notes.

 

QQ meeting for LTSP 

Infrastructure of COLD and 6GeV linac is critical to the budget estimation.

Requested by JeanDaillant discussion with BIG + requirements from other divisions.

How we can construct a full energy linac.

The estimation of the is quite critical for the long-term scientific plan.

Would also need to spot any other requirements, for example, from vacuum,

 

Presentation by YGouez

 

We start with just a red line on a on a picture.

Just keep in mind that the objective of this exercise is very rough. It's not a proper solution. It's just to talk about issue and to try to evaluate the impact of the closure of the building, to evaluate the time and the cost to mitigate the impact.

Objective to open the discussion and to discuss what can be done and what can be adjusted. Clearly, right now, there is no real strategic construction and no real cost estimates, because we don't have enough information for what you need.

 

So in dark blue, you have the footprint of the building, but could be the building. And then in gray, it's the footprint of the work area that we show. So it's 140 meter long. It's about 40 meter wide.

 

SL: When you say 140 meters, it's only the main rectangle or also the little rectangle? 

YG: No, it's only the big blue one. 

SL: the small blue rectangle could be also considered in the 140m, making the main building shorter.

YG: we don't know how the new building will be connected with the existing one

 

Qing Qin: One floor, two floors…

YG: one floor. We don't consider the stage as the option with two floor. We only consider the one floor building. difficult for me to imagine how you will move your equipment inside, what would be the size of the roof and so on. My goal was to try to evaluate the impact. So I just consider one solution, one of them, the worst case (larger building).

 

Cost compared to BM18 400m2 = 3 million euros

 

The new building is about  2,000  square meter. it will be between 10 and 15 millions euros.

 

We'll have to ask probably a company to help us on this estimate when we have more details settled.

 

For example the thickness of the walls and the material of the walls are unknown. To be confirmed by safety. And when everything's consolidate, you can send me as a data and we'll.

 

SL: walls slab and roof are to be as the 6GeV SR tunnel. The linac beam will be 6GeV.

PC: confirm.

 

YG: must cut the wall and for the to create the connection between the booster and the new building. The cost is between 2 and 300 euros. And because the main time that we need is to cut. Probably need around one month.

 

SL: So instead of cutting the wall, you just need to drill a hole to make a big pipe of 60 millimeter go through. YG: If you just need this, yes, it would be easier. That makes us spare three meters.

 

YG impacted rooms are in yellow

 

Electrical substation supply line ID 24, BM25, BM26, BM26, BM28, and so on. The sectors, the MTBN buildings, but also the MTBB buildings…

This electrical substation supplies one-third of the experiments and part of the CTRM, CTRM, mainly the office. We need to find a space, a new area, a place, and it's costly because it's made between 600 and 900 kilo Euro only for the equipment.

 

SL: In any case, we need likely another electrical substation for the linac itself.

YG: yes, but this will be a different one. Also the linac will be Process Network while the substation is for Facility network.

 

Qing Qin: So how long time for this impact on ASD equipment? For example, no electricity and also long time for the .

 

YG: The impact is only for the light and the socket in the office. So normally, all the technical groups will still be supplied. The control room is still supplied.  Storage ring could operate, but one third of the beam lines cannot do it.

 

Jean-Luc Revol: Okay, and you can prepare it and switch from one to the station. During the shutdown.

 

YG: Not during a shutdown. We need more than one shutdown. That's why the estimate is we need at least two years before to move to the next substation.

 

Jean-Luc Revol: So you need 2 years to prepare. But how long you need to switch?

 

YG: t's difficult to say. There is very big cable. There is a lot of cable.

It's just that I have no solution to present. I have only an issue. We don't study this today. Hope we can realize the work. Just give you some idea of mitigation

 

SL: if space is needed, we can try to figure out other solutions for the linac that result in less impact on the buildings

 

YG: moving from one meter or 2 meter will not change a lot

 

For the MTB-Nord, if we destroy the building, there is no reason that we keep this segment. But if we look at what kind of network goes through MTB-nord, here you have a view. It's plenty of cable. It's plenty of freeze networks.

 

 

 

Cut the booster wall to create connection of buildings.

Main time is to but the booster walls (1month minimum). 

 

SL: could simply pass in the vacuum pipe (16mm radius hole)

 

3 years to build 

 

Electrical substation supply 1/3 of EXPH. 

 

Electrical gustation could be displaced. 

 

ALGE room could be used for the electrical substation

 

Facility network substation. For linac need Process machine network protected by HQPS. 

 

ASD equipment no electricity small impact. CTRM. Still elec for all equipment inside CTRM. Lights and sockets in the office. 

 

1/3 of the beam lines do not operate. 

 

Need more than 1 SD to replace the electrical substation. 2years to prepare. Switch during a SD. Big cable, a lot of cables. 2 weeks to replace the main electrical switchboard. Move cables, more time. Do it bit by bit during small SD. 

 

SYTU technical room (vacuum) must reinstall somewhere else. Also possible only during SD and needs space.

 

Corner of the booster building. 

Exit from SYTU will be removed.

 

COST is only for the building. Infra is not included.

 

When trucks crossing the bridge. Does this disturb the beamlines? 

Not so many trucks every day. 

Could take some measurement during delivery. 

 

PC: time needed if operation go on. Vs time if stop operation.

YG: must list work that create disturbance and sum all of it to have an idea. 

 

Building construction == 1year. + 2 month for demolition MTBN

 

Moving networks plenty of weekly interruptions. Distributed during the SDs. 

 

Much easier to do works on a long SD rather than in bits here and there. 

 

 

During booster tunnel works no beam. Minimum 4month of SD. 6month more likely. 

 

First evaluate what will impact beamliyne. Building will have an impact (vibration) suppression of earth and suppression of tunnel wall booster. 

 

Need duration of each phase. 

 

Building construction is long. 

 

 

Need size of walls

If you know if we can remove the earth embankement

 

Need maintenance requirements, how to move equipment

 

CN using the existing linac.

 

QQ underground is possible? 

Water is a problem. 

CM easier to be higher than lower. For safety. 

 

Water at 1m below ground level. 

 

For next meeting :

Find location that has least dark time 

 

Work together to find the least impactful location. Impact in operation, then we will be able to decide. 

 

New building or adapt existing one. 

 

Annabelle will organize a meeting:

YG JLR SL TB

To decide location of the building 

 