14th COLD meeting
CTRM
Meeting 28th September 2026
Present:
SL (BD)
BJ (OPE)
JLR (OPE)
IL (OPE)
HPM (VAC)
PC (Safety)
PF (PSG)
PB (RF)
TB (MEG)
TR (ACU)
FE (DIAG)
NB (DIAG)
QQ (Dir)
Zoom not available
Discussion
WP01
Purchases ok
WP02
Screen monitors. Discussion with DESY.
2 screens at end of TL2
WP03
Started vacuum simulations for the cavity.
Cryomodule rather difficult.
Chamber would be simpler if as in-vaccum devices
Pumping from waveguides most relevant.pumping from sides (iris)
Next Step: Add pumps to drawing
2nd cryomodule: as close as cryoinvacuum. Simple and work well.
WP04
First sketch for RF waveguides.
Rough mechanical drawings (to send today or tomorrow) to P.Berkvens for Safety simulations.
Full installation will move toward entrance door (further away from present linac)
Discussion with BIG to define LN2 distribution and water cooling.
WP05
No update
WP06
Every WP check request for ELECTRICAL cubicles.
Think about power for each cubicle
Kind of cable needed to be installed by BIG. Start list on Excel document
Cables will be on the same Database as EBS. COLD project cables naming managed by BIG.
Need to calculate electrical power needed. If above 3000W signal to electrical unit to specify specific PS.
If doubts on numbers of cubicles.
RF group cubicles for LLRF still doubt. To be checked after LLRF quotation
WP07
No much progress
Progress with control of scandinova modulator . Works well. Still missing diagnostics such as waveforms to be reported in tango devices.
Not easy support from scandinova.
PB: technicain from Scandinova on site to debug modulator.
WP08
No update
WP09
Calculations still on-going.
PSS found solution.
Switch from primary doors LB1 - to fence. Prevent switching off rips.
People will enter first part of linac without impact on accelerator.
Will implement during October SD. Ready for January restart for conditioning of RI accelerating structures.
WP 10
PSG will buy 4 new PS for Quadrupole magnets. Will use spare part PS for the corrector and dipole magnet.
WP11
Cathode alignment angles are relevant issue.
Cathode is flat or rounded?
Shutdown activities
Crane during USM. Is OK.
PSS will be modified?
Removal of Faraday Cage beginning of November
Safety corridor on faraday cage side
G.Chazot working on a work permit JLogbook. Every one that has works to do on Linac upgrade, cold, or booster:—> fill JLOGBOOK work permit. Stating specificity of the work.
I.Leconte will centralize all activities.
QQ: move to TDR. Try to get by next Spring (2027).
JLR: could add Phase 2 and 3.
QQ: let’s wait for SAC and council to see overall LTSP
MEG COD waiting for Administration papers.