7th COLD meeting
CTRM meeting room
present:
A.D'Elia, B.Joly, J.-L. Revol, P.Borowiec, T.Brochard, H.Pedroso Marques, S.White, N.Carmignani, R.Bourtenberg, G.LeBec, Qing Qin, C.Gonzales Torres, F.Ewald, L.Eybert, B.Roche, Y.Gouez
presentation of review pannel
WP01 ADE
2 COD being hired. 1 for LLRF, 1 for RF engineer
N.Benoist (DIAG) accepted to help T.Brochard for RF waveguides drawing. Hours needed to be defined.
contact with infrastructure WP05 for cooling and elec requirements.
WP02 FE
no update
WP03 HPM
no update
WP04 TB
to prepare meeting with SLAC on pressurized vassel, contacted APAVE. if pressure rise lower than 0.5bar, then no need for any authorization.
What about boiling LN2 or issues? This is handled by burst disk pressure limitation valve.
START of next year 2026 first drawings.
drawings inspected. some missing part. moving parts not all clear. some manual movements some motorized.
no alignment reference points.
CGT : need to define alignment strategy to define the ref-points locations.
SL: we could propose a solution to SLAC
LE: 50 um are demanding alignment request.
SL: this value is based on 6GeV (COLD phase 4) simulations.
WP05 YG
new round of meetings with various WPs.
for cooling system a new installation will be needed for COLD. fully independent from ESRF present linac.
electricity not a big deal
LN2 tank size to be confirmed ( < -- ACTION)
Space configuration to be evaluated. Space for control room will then be defined (common for linac and COLD project)
SL: if the use of COLD and present linac is alternative (never work together) the water infrastructure would be sufficient?
PB and SW: in any case better to have separate installation.
not easy to install new pipes (bigger)
WP06 BJ
waiting fro drawings
control room for acustic insulation (safety + RF)
modify linac entrance building to have larger platform and cover in case of rain. Not expensive installation.
WP07 RB
gathered needs for COLD
interlock meeting. Marc Dubrulle provided a list of interlock. some are for PSS some for equipment interlock.
WP12 TIMING (no referent at the moment, replaces WP photons)
PSI set up will work for COLD project phase 0,1 and 2. For phase 3 a system able to send beam in the SR will have to be designed.
BR: PSI solution will work for COLD project phase 0,1 and 2
WP08
no update
WP09 JLR on behalf of SAFETY
linac door connected to PSS system in winter shutdown.
meeting monday 15th dec 2025 with SAFETY
authorization for RF unit ready, but not submitted
SL: AFTER the authorization is submitted (to avoid any further delay) could we ask to submit authorization for RF unit to arrive in March 2027? Identical document, only RF-unit number will change.
WP10
no update
WP11
re-running linac simulations due to bug fix in RF_Track code.
WP12-photons suppressed after meeting with FEL experts. nothing to learn from undulator after cold linac installation.
visit of CTF-2 and CLEAR facility very fruitfull. Same installation as ours.
CDR ACTIONS:
remove phase 4 from all sections apart sections intro and beamdynamics. ( < -- ACTION)
remove BLM section from CDR ( < -- ACTION)
add name of people writing to every section ( < -- ACTION)
SEND CDR PDF to Yann Gouez ( < -- ACTION)
ADD new structure design for COLD Phase 2 installation ( < -- ACTION)
remove JIRA PLAN and replace it with link to microsoft project ( < -- ACTION)