16th COLD meeting
MD-1-21
NOTES:
Present
S.Liuzzo
B.Tommasini
G. Chazot
C. Gonzalez Torres
P Colmp
H.Pedroso Marques
T Brochard
R Bourtenberg
T.Rozier
C Benabderrahamane
A. D’Elia
F. Ewald
Remote:
B.Joly
JL Revol
G Le Bec
D Martin
Discussion:
WP 01
Meeting with Spinner last week. Hope to launch CFT for the waveguides this year. May be also LLRF CFT.
Some problems with the loads (administrative problems for warranty from Japan)
Direction couplers are moving well.
All infra for modulator is progressing according to plan.
End of November FAT of Modulator in Scandinova. A.DElia and MDubrulle will go.
Need cabinets specifications.
Last week LCWS workshop. All fine.
WP 02
No update
WP 03
Outgassing of WAVEguides measurements. 2m.
ADE some simulation plots already shared with RF
WP04
Last week drawing sent for the marks in PINJ.
Also halls on the wall.
CGT: could extract a file of coordinates?
TB. OK
Following meeting with spinner, improved waveguides layout. Will feedback with WP01.
ADE: first time that we do CFTon waveguides on this frequency. Technical specs must be carefully considered.
Ema progressed on the support of the quadrupoles. 10nm resolution not possible.
Beam dump definition on 1st December.
Work with TID for LN2 infrastructure.
Need to discuss with Safety to present LN2 project for COLD. Before end of November.
WP 05
Meeting on 6GeV linac building.
JLR Impact of construction on operation is critical
JLR Vibration of works also critical
WP 06
Faraday cage removed from Modulator hall
Electrical cubicles ordered and delivered before Christmas.
Install end of January beginning of February.
WP 07
No update
Could be interesting to have a Linac simulator?
RB and TR yes. Could be interesting.
Interlocks update meeting
WP 08
Drawing received.
Drawings before SD.
SL. No, before cranes installation.
ADE: need modulator and crane
This anticipates the foreseen marking.
Likely cranes installation week 49
WP 09
Safety.
Waiting meeting on 1st December.
+ meeting LN2 infrastructures
First skatch can discuss on that.
WP 10
Magnets received specifications. Especially corrector. Easy magnet to do.
Finalize quadrupole good field region. Need from BD.
16mm external diameter of vacuum chamber.
BD action.
WP 11
Solenoid displacement specifications needed only for GUN CFT.
Presentation on emittance.
WP 12
No update
G Chazot presentation on Electronic logbook
Trace all interventions for COLD until booster upgrade.
Lock out responsibility. PSG or BIG elec. workflow updated to take in account the remarks of the last meeting.
presentation.
Operation approves before sending to safety for approval.
Lock out if needed. Operation completes the form with PSG or BIG elec. Approves the permit. Then moves to safety.
Before starting intervention, operation valid the lock out done by big elect.
If all is ok, form shows the status and intervention a start.
After intervention the person in charge of the intervention acknowledge the end of intervention and lock out release could be done if needed. + safety if feedback needed.
Gaant view of the intervention in calendar as well.
See interventions in parallel.
Color meaning = project (COLD, booster, etc.. ) it is just an example. Can be selected.
I Leconte is ready to start using this work permit from now for the COLD project.
ADE last time there was some problem wth BIG. Is the procedure now agreed with them?
GC they will do the work as usual. ILeconte will take the paper form and enter it in the permit to work.
ADE when working on klystron. Need to lock out high voltage. Final action is call BIG to do lock in lock out. Some key go from RF to BIG and viceveresa. Who needs to be called for this actions?
For example to open garage for klystron.
GC: operation takes the info from logbook and calls the required teams to do the lock out.
ADE Operation can not tell. BIG and SAFETY have to tell if it is safe.
JLR procedure will be as usual, only the paper work will become partially electronic. It will not be the logbook to give permission to work.
EIC will be submitted February
LLRF person, 5 people to interview as soon as possible. Zoom then in person.